Trial runs of $2.6 Billion Subansiri Lower Hyrdo Power Project soon

First Published: 13th June, 2023 17:40 IST

State-run NHPC Ltd. will start trial runs in July for the Subansiri Lower project that runs through the states of Assam and Arunchal Pradesh.

India is close to starting a mega hydropower project that has been in the works for 20 years, a key step in the country’s energy transition.

State-run NHPC Ltd. will start trial runs in July for the Subansiri Lower project that runs through the states of Assam and Arunchal Pradesh.

The first unit is expected to be commissioned in December, according to finance director Rajendra Prasad Goyal. By the end of 2024, all eight units will be commissioned, he said.

Hydropower, with its ability to quickly respond to fluctuations in electricity demand, is seen crucial for balancing the grid as intermittent generation of solar and wind power rises. However, the 2-gigawatt project, started in 2003, was delayed by protests and litigation, driven by concerns over environment damage.

The cost of the project jumped to $2.6 billion, more than three times the original estimate. The National Green Tribunal allowed the work to resume in 2019 after eight years of suspension.

“We need to get nearly 40 approvals from different departments before we start building a hydropower project. All the scrutiny should be done at this stage,” Mr Goyal said. “Any stoppages after the construction has begun is problematic.”

Large dams are also country’s way of boosting local economies in areas along its tense borders with China and Pakistan. As Subansiri approaches conclusion, NHPC is finalising plans to award construction orders for the 2.9-gigawatt Dibang project, the biggest hydropower plant India has planned to build.

Listen to the latest songs, only on JioSaavn.com

To spur hydropower, the government has given large dams clean energy status. This forces provincial power distributors to prioritize purchase of hydropower ahead of electricity produced from fossil fuels.

The government has also agreed to give budgetary support in some cases on civil construction and flood moderation work.

Also Read : Floods and erosion rear its ugly head in Dibrugarh

COMMENTS

Leave a Reply

Your email address will not be published. Required fields are marked *

WE RECOMMEND

Banner
Northeast to get 4 KVs and 17 JNV schools. Check Details Here

These moves are expected to benefit around 82,560 students through the new KVs and 15,680 students through the new NVs.

07th December 2024
Banner
Arunachal: Insurgent Outfit NSCN (K-YA) Issues Extortion Note of Rs 20 Lakh to Oil India Limited

Top company officials, including the Chief Managing Director (CMD), are in touch with the Government of Arunachal Pradesh regarding the matter.

03rd December 2024
Banner
Father’s Heartfelt Plea: ‘Shun Violence, Come Home’ A Tearful Appeal to Son Leading NSCN (K-YA) Extortion in Arunachal

"I feel deeply ashamed. Is this the life you want to lead forever?," said Meekong Mossang.

02nd December 2024
Banner
Anini Wins Gold at Outlook Traveller Awards 2024 for Best Offbeat Mountain Destination

Anini, in the Dibang Valley of Arunachal Pradesh, has earned the prestigious Gold Award for Best Offbeat Mountain Destination.

01st December 2024
Banner
Arunachal CM Pema Khandu Holds High-Level Meet, Reviews Progress of Upper Siang Multi Project

“This project is critical to ensuring the peaceful and prosperous existence of the Siang Basin and our Adi brothers and sisters”, Khandu stated.

30th November 2024