Northeast India’s Only English and Hindi Satellite News Channel

NF Railway achieves breakthrough in Sivok – Rangpo new rail link project

First Published: 28th February, 2024 20:52 IST

The Sivok – Rangpo new rail link project connecting Sivok (West Bengal) and Rangpo (Sikkim) is about 45 kms long and is characterized by 14 nos. tunnels, 13 major bridges,

In a major milestone the 2nd longest tunnel no. T-01(4224 meters long) to the Adit of the Sivok – Rangpo Rail Project (SRRP), located in Darjeeling District of West Bengal, achieved a breakthrough on February 27, 2024.

With the tunnel breakthrough, mining activities have been successfully accomplished in all the Adit tunnels of this project.

The length of the main tunnel of T-01 is 4224 meters, along with an Evacuation tunnel of length 855 meters situated near the Coronation Bridge in Darjeeling district, West Bengal.

The main tunnel traverses through vulnerable and challenging geological and seismic conditions of the Younger Himalayas. Like all other tunnels in the SRRP, to counter vulnerability of the ground mass, latest and most sophisticated tunneling technology, i.e., New Austrian Tunneling Method (NATM) has been used here.

The Sivok – Rangpo new rail link project connecting Sivok (West Bengal) and Rangpo (Sikkim) is about 45 kms long and is characterized by 14 nos. tunnels, 13 major bridges, 09 minor bridges and 5 nos. stations.
The length of the longest tunnel (T-10) is 5.3 km and length of longest bridge (Br-17) is 425 meters. About 38.65 kms of the entire project alignment is passing through tunnels. 91.59% of the tunneling work has already been completed.

At present final lining has been completed in tunnel T-14& T-09 and is under progress in tunnel T-02, T-03, T-05, T-06, T-07,T-10, T-11 and T-12. Total 10.89kmlining has been completed till date.
Work in all sections is being carried out round the clock 24×7.

This is one of the most prestigious ongoing National Projects in India and on completion of this project, first time the state of Sikkim will be connected via railways. This rail network on its completion is aimed to provide alternate connectivity to the state of Sikkim.

At present all the activities related to construction of tunnels, bridges and station yards are going on war footing for early completion of the project.

COMMENTS

Leave a Reply

Your email address will not be published. Required fields are marked *

WE RECOMMEND

Banner
Gurugram Businessman Loses Rs 1.99 Lakh in Fake Sikkim Resort Booking Scam

According to Sabharwal, a resident of DLF New Town Heights, Sector 90, he planned a family trip to Sikkim on March 3.

24th March 2025
Banner
Sikkim Congress slams SKM Govt for not being able to fulfil Limboo-Tamang seat reservation in State Assambly

Congress MP Ulaka also questioned the silence of the Double Engine government on resolving the issues.

23rd March 2025
Banner
Sikkim Launches Thrilling Bungee Jumping Experience at Asia’s Second-Highest Bridge

Sikkim Bungee Jumping: The state’s first-ever bungee jumping facility was officially inaugurated today at Singshore Bridge

22nd March 2025
Banner
Railways Ministry Considering Melli-Dentam Railway Link to Improve Connectivity in South and West Sikkim

Melli-Dentam Railway Link: The Railways Ministry is actively considering a proposal to connect the southern and western regions of Sikkim with a new railway line, with a feasibility survey currently in the works. The proposed 75 km railway link would cover key locations, including Melli, Jorethang, Legship, and Dentam. Lok Sabha MP Indra Hang Subba […]

19th March 2025
Banner
Final Draft Report on Tribal Status for 12 Left-Out Sikkim Communities Likely After High-Level Meeting in Kolkata

High-level sources have confirmed that this meeting will focus on the final discussion of the draft report, which was previously discussed on February 10.

16th March 2025