Aizawl to be in railway map in next two years
First Published: 24th April, 2021 22:19 IST
Mizoram capital Aizawl will be on the railway map in the next two years as construction of the 51.38 km long stretch of the broad gauge railway line between Sairang
Mizoram capital Aizawl will be on the railway map in the next two years as construction of the 51.38 km long stretch of the broad gauge railway line between Sairang and Bairabi on the Mizoram-Assam border is expected to be completed by December 2023, a railway official said.
Sairang is about 20 km from Aizawl. The Northeast Frontier Railways (NFR) official said on Friday that work is in progress at different stages and almost all tenders for various works have been finalised.
He said that 89.55 per cent of earthwork, 37 per cent of major bridges and about 73.26 per cent of minor bridges have been completed.
Twenty one per cent of the construction of cut and cover tunnels has also been completed, he said.
There are 32 tunnels (12.67 km total length), 16 cut and cover tunnels (2.58 km total length) along the 51.38 km long stretch of the broad gauge railway line, which traverses through Thingdawl and Tlangnuam Blocks of Kolasib district and Aizawl district.
There are 55 major bridges of which six are tall bridges having a height of more than 70 m (the tallest being 101.4 m), 87 minor bridges, five road overbridges and eight road underbridges.
Apart from Bairabi, the railway line will pass through four stations – Hortoki, Kawnpui, Mualkhang and Sairang.
Mizoram chief secretary Lalnunmawia Chuaungo on Friday visited various construction sites of the BG line and interacted with railway officials.
He shared positive feedbacks with the NFR officials and urged them to expedite the construction.
Chuaungo assured the commitment from the state government to tackle any issue that might hamper the construction works.
He exuded hope that the project when completed will unlock the untapped economic potential of the state.
The foundation stone of the Sairang-Bairabi broad gauge line was laid by Prime Minister Narendra Modi in November 2014.
The project was started in 2015 and was initially scheduled to be completed by 2018.
The project could not be completed on time due to several hurdles, including hilly terrain, deep valleys and gorges, frequent landslides, short duration of working season due to monsoon and lack of labour and construction materials in the state.
The project when completed will open good economic opportunity as commodities will be transported in much cheaper, cost-effective, and eco-friendly way and state farmers will be able to send their produce to the wider market of the various states at a cheaper rate and in a time-bound manner. PTI
COMMENTS
TOPMOST STORY NOW
Live Manipur: Job Card Holders Protest in Churachandpur Demanding Release of Pending Wages Before Christmas
23rd December 2024Live Manipur CM Urges Unity Among Communities at IRB Passing Out Parade in Assam
23rd December 2024Live Child Artiste From Mizoram, Esther Hnamte Wishes Everyone A Merry Christmas And Happy New Year
23rd December 2024Live Mizoram: Christmas & New Year Wishes from Zaipawl Diocese
23rd December 2024WE RECOMMEND
Mizoram: BJP Set to Form Government in CADC with 3 ZPM MDCs Joining Party
BJP has gained a political advantage as three MDCs from the ZPM joined the party on December 21
22nd December 2024Safeguarding Northeast’s Identity and Culture Top Priority: Home Minister Amit Shah at NEC Plenary
Amit Shah further stressed the need for a shift in focus from countering extremism to empowering citizens with constitutional rights.
21st December 2024Aizawl Faces Internet Slowdown Due to Multi Utility Pole(MUP) Project For Upgradation of City’s Infrastructure
The project has led to significant delays in internet services, affecting residents and businesses alike.
20th December 2024Two Women Prisoners from Myanmar Use Scissors to Escape from Mizoram’s Champai Jail. Here is How
Lalchhanmawii is a repeat offender as she had escaped from Aizawl Central Jail in Nov 2023 and was re-arrested in May 2024.
19th December 2024Indigenous Identity at Risk, NEIPF Urges NE MPs to Take Action to Stop Influx of Myanmar and Bangladesh Refugees into Northeast
The NEIPF is planning to meet all the CMs of the Northeastern states for meaningful discussions
19th December 2024