Aizawl to be in railway map in next two years
First Published: 24th April, 2021 22:19 IST
Mizoram capital Aizawl will be on the railway map in the next two years as construction of the 51.38 km long stretch of the broad gauge railway line between Sairang
Mizoram capital Aizawl will be on the railway map in the next two years as construction of the 51.38 km long stretch of the broad gauge railway line between Sairang and Bairabi on the Mizoram-Assam border is expected to be completed by December 2023, a railway official said.
Sairang is about 20 km from Aizawl. The Northeast Frontier Railways (NFR) official said on Friday that work is in progress at different stages and almost all tenders for various works have been finalised.
He said that 89.55 per cent of earthwork, 37 per cent of major bridges and about 73.26 per cent of minor bridges have been completed.
Twenty one per cent of the construction of cut and cover tunnels has also been completed, he said.
There are 32 tunnels (12.67 km total length), 16 cut and cover tunnels (2.58 km total length) along the 51.38 km long stretch of the broad gauge railway line, which traverses through Thingdawl and Tlangnuam Blocks of Kolasib district and Aizawl district.
There are 55 major bridges of which six are tall bridges having a height of more than 70 m (the tallest being 101.4 m), 87 minor bridges, five road overbridges and eight road underbridges.
Apart from Bairabi, the railway line will pass through four stations – Hortoki, Kawnpui, Mualkhang and Sairang.
Mizoram chief secretary Lalnunmawia Chuaungo on Friday visited various construction sites of the BG line and interacted with railway officials.
He shared positive feedbacks with the NFR officials and urged them to expedite the construction.
Chuaungo assured the commitment from the state government to tackle any issue that might hamper the construction works.
He exuded hope that the project when completed will unlock the untapped economic potential of the state.
The foundation stone of the Sairang-Bairabi broad gauge line was laid by Prime Minister Narendra Modi in November 2014.
The project was started in 2015 and was initially scheduled to be completed by 2018.
The project could not be completed on time due to several hurdles, including hilly terrain, deep valleys and gorges, frequent landslides, short duration of working season due to monsoon and lack of labour and construction materials in the state.
The project when completed will open good economic opportunity as commodities will be transported in much cheaper, cost-effective, and eco-friendly way and state farmers will be able to send their produce to the wider market of the various states at a cheaper rate and in a time-bound manner. PTI
COMMENTS
TOPMOST STORY NOW
Live Wayanad bypolls: Priyanka Gandhi Vadra leads with 5,672 votes; CPI, BJP candidates trail in 2nd, 3rd spots
23rd November 2024Live Counting begins for Jharkhand, Maharashtra elections, along with bypolls across 15 states
23rd November 2024Live Indian national indicted for illegal export of US aviation components to Russia
23rd November 2024Live 12 Bangladeshi Nationals Including 4 Children and Women Detained in Tripura
22nd November 2024WE RECOMMEND
Clean Air Crisis Looms Over Mizoram: Alarming Deterioration Observed Despite High Forest Cover
The Mizoram Pollution Control Board has sounded an alarm over the gradual deterioration of the state’s air quality.
22nd November 2024As Delhi Gasps for Clean Air, Aizawl Boasts of Cleanest Air with AQI of 29, How Does It Do It?
At a time when national capital Delhi has become the most polluted city with most poisonous air quality posing threat to people’s lives, and other parts of the country are grappling with poor air quality, Aizawl, the capital city of Mizoram, has achieved an impressive milestone, topping the country’s air quality chart with an Air […]
21st November 20248 More Football Players Banned for Match Fixing in Mizoram Premier League
The fresh bans bring the total number of banned players to 33
20th November 2024Mizo Defence League Issues Ultimatum for Meitei Community to Leave Mizoram by November-End
This resolution comes in the wake of the recent killing of 10 armed individuals in Manipur's Jiribam district.
16th November 2024This Mizoram Professor Teaches Without Pay. Here is Why
Despite challenges posed by the COVID-19 pandemic, he successfully mentored 7 students who achieved university rankings.
15th November 2024