Shillong water crisis: More tough days ahead says Meghalaya Govt

First Published: 27th November, 2023 21:30 IST

But the government has worked out a plan to resolve the issue that has delayed the third phase of Greater Shillong Water Supply Scheme (GSWSS) pending release of land by

Reported by Purbasha Bhattacharjee

Meghalaya PHE Minister Marcuise N Marak said on Monday that Shillong, the capital of Meghalaya and a tourist hotspot, might face some tough times as the city might face shortage in water supply due to delay in the completion of phase III of the Greater Shillong Water Supply Scheme (GSWSS).

Speaking to Northeast Live, Marak said, “Yes we can expect that (shortage in water supply) because the 3rd phase of Greater Shillong Water Supply Scheme (GSWSS) Phase III which is pending because of Hima Mawphlang not cooperating with the department. Till now we are waiting for the plot of land which they are supposed to give to the PHE department. Just because of that we are stuck up. If we get that plot of land, construction for the phase-2 tank of Shillong water supply scheme would have been started. So we are just stuck up there. Once that is done, water is plenty in the Umiam river, it is ready. Rest in terms of the distribution, there are 12 zones, for which work has been completed for 2 zones and the rest are under construction.”
“There were lots of hindrances like clearance from forest department, from cantonment board, PWD, all these issues are settled now. Only the Hima Mawphlang issue is remaining. So once that is done we will be able to start. I hope if it is done we will be able to resolve the water crisis in the Shillong city,” Marak added.
However, the Meghalaya Government has worked out a plan to resolve the issues once and for all by accepting a condition put forward by the Hima Mawphlang.
Sharing more details about this, the Meghalaya PHE minister said, “Regarding Hima Mawphlang several issues had cropped up with them but finally we are just about to get it resolved. They have requested for government employment of 22 persons, the government has agreed to that. The Chief Engineer has already issued a letter saying that they should be submitting their list of people, whom they would be recommending for employment. So, the government has already agreed but just waiting for their (Hima Mawphlang) application to the department. Once that is done we are ready to give them appointment.”

Also Read: Meghalaya: Oil tanker drivers to strike work from Nov 29, petrol-diesel supplies might get hit

COMMENTS

Leave a Reply

Your email address will not be published. Required fields are marked *

WE RECOMMEND

Banner
Meghalaya Sees Surge in Violence Against Women with 628 Cases Reported in 2023

East Khasi Hills District recorded the highest number of incidents.

25th November 2024
Banner
Irrespective of Inquiry Outcome, VC Won’t Be Allowed Back Says NEHU Community

VC Shukla has gone on leave after the students’s protests intensified and the Meghalaya government stepped in.

25th November 2024
Banner
Two-Member Inquiry Panel Reaches NEHU to Probe Mismanagement Allegations

The committee has been tasked with submitting its report within 15 days, providing necessary recommendations for corrective action.

25th November 2024
Banner
Meghalaya: Assam Rifles Half Marathon 2024 Kicks Off In Shillong

Legendary boxer and former Rajya Sabha member MC Mary Kom, who was the event's brand ambassador, also participated in the 10 km "Pine Path" run.

24th November 2024
Banner
We Don’t Have Culture of Use and Throw: CM Conrad on Allies After Wife Wins Gambegre, Party Tally Goes Up to 32

Mehtab Chandee registered a convincing win in Gambegre helping the ruling NPP take its tally to single majority mark of 32.

23rd November 2024