Signed several MoUs, not a single pvt power project took off: Meghalaya Power Min

First Published: 11th August, 2023 12:49 IST

NEEPCO which has signed an MoU for the implementation of a 500-megawatt thermal power project in the state also withdraws the project

As Meghalaya continues to face severe power outages due to the withdrawal of several independent agencies from the implementation of power projects in the state, State Power Minister AT Mondal said that the state government has signed several Memorandums of Understanding (MoU) with independent agencies, but not a single power project took off till date and even many MoUs have been cancelled.

Speaking to media at his office, Minister AT Mondal has informed that the North Eastern Electric Power Corporation Limited (NEEPCO), which has signed an MoU for the implementation of a 500-megawatt thermal power project in the state has also conveyed its decision not to continue with the project.

“NEEPCO communicated its intention to terminate the thermal power project, highlighting a shift in focus towards exclusively green and clean energy endeavours.

He said that the matter was taken up with the Chief Managing Director (CMD)of NEEPCO in New Delhi.

Minister Mondal said that another company named DS Group had signed an MoU for a thermal power project but there is no communication from the company’s end.

Stating that the state government is mostly focused on hydel power projects and not thermal projects, the Minister maintained that hydel power projects have various advantages.

Speaking on the Kynshi Hydel Project, Minister Mondal said that the government will scrap the old MoU as the independent party has come up with a new model which according to them is more viable.

The Power Minister said that no penalties were levied by the State government against these independent agencies.

Besides Umiam, other hydro projects in the state are run-of-the-river projects and they operate at full capacity during the rainy season.

The state can produce up to 5 million units of power on some good days but only around 1 million units on less productive days.

COMMENTS

WE RECOMMEND

Banner
Bad roads in North Garo Hills: NPP MLA Rupert Momin assures Govt action

Recently, AITC MDC from Rongrong constituency, Rinaldo K Sangma had alleged that a single repair work has not been undertaken since 2018, despite the CM 's assurance to construct new road.

19th May 2024
Banner
“Support of Meghalaya’s people has been our strength throughout”, DGP LR Bishnoi’s heartfelt speech on his retirement

He thanked CM Conrad Sangma for guiding him and the entire police force through the labyrinth of challenges, the state police had to face during its war on drugs in the state.

19th May 2024
Banner
Meghalaya govt in talks with BCCI for setting up cricket stadium of international standards in Ri Bhoi

Meghalaya Sports Minister Shakliar Warjri informed that the state Government is in talks with BCCI in this regard

18th May 2024
Banner
Shillong Medical College to be operational by 2025, Tura medical college by 2026-27: Ampareen Lyndoh

Meghalaya Health Minister Ampareen Lyngdoh on Friday informed that the Shillong Medical College is likely to be made functional by September 2025 and the Tura Medical College by 2026-2027.Chief Minister Conrad K. Sangma held a review meeting on Friday with officials from the Health Department, in the presence of Health Minister Ampareen Lyngdoh, to discuss […]

18th May 2024
Banner
Meghalaya CM Conrad Sangma chairs key meet of DCs and SDOs in Shillong

“The conference is very crucial as the feedback we receive from DCs and SDOs is important for the public at large,” the Chief Minister said.

17th May 2024